These figures are taken from estimates of two
building companies in 1999 :
- Lambert for masonry - Croix André for carpentry
MAJOR WORK :
Masonry Carpentry / propeller shaft / wheel and
brakes Battening / roofing / water-proofing
TOTAL |
304.917,41 FHT 411.450,08 FHT 117.911,22 FHT
834.278,71 FHT |
46.484,36 € 62.725,16 € 17.975,45 €
127.184,97 € |
SECONDARY WORK :
Vanes and sails Beams / joists / flooring Exterior
carpentry / staircase Grinding mechanism
TOTAL |
135.548,75 FHT 84.270,00 FHT 38.478,00
FHT 267.226,00 FHT
525.522,75 FHT |
20.664,27 € 12.846,88 € 5.865,93 € 40.738,34 €
80.115,43 € |
TOTAL COST OF WORK :
Total building costs before taxes Architect's fees 12%
Diverse
TOTAL, before taxes VAT 20,6%
TOTAL, Taxes Included |
1.359.801,40 FHT 163.176,16 FHT 110.500,00 FHT
1.633.477,56 FHT 336.496,36 FF
1.969.973,92 FF |
207.300,38 € 24.876,05 € 16.845,62 €
249.022,04 € 51.298,54 €
300.320,58 € | |
| |